OBJECTIVES OF SCHEDULING
Other Chapters
ASPECTS OF CONSTRUCTION MANAGEMENTBUILDING CONTRACTSTENDER AND CONTRACTSOBJECTIVES OF SCHEDULINGOCCUPATIONAL HEALTH AND SAFETYACCIDENTS
- Q1: Define Scheduling.Ans: A table showing the proposed duration of the construction of various items of work is known as schedule. The process of preparing such schedules is called scheduling.
- Q2: Define Bar Chart.Ans: The scheduled program of various activities is represented by a number of bars and hence the method of scheduling is known as “Bar Chart”.
- Q3: Define Critical Path Method (CPM).Ans: Critical Path Method (CPM) is a project management technique used to identify the longest sequence of dependent tasks in a project, which determines the shortest possible time to complete the project.
- Q4: Define Critical Path.Ans: It is the chain of tasks that must be completed on time; if any task on the critical path is delayed, the entire project will be delayed.
- Q5: Define Material Schedule.Ans: Moving & storing of materials in any form is known as “Material Schedule”. It is a schedule which shows the date of delivery of each type of material at site.
- Q6: Define Labor Schedule.Ans: Graphical representation of the labor requirement on certain days or during certain works is known as labor schedule.
- Q7: Define Equipment Schedule.Ans: It shows the type and quantities of equipment required on particular dates in the entire project. This enables the engineer to make proper arrangements.
- Q8: Write the importance of Scheduling.Ans: In Post-Tensioning, the prestressing force is applied to the steel tendons after the concrete is placed and cured.
- Q9: Define Float.Ans: It is the time by which activities can be delayed without delaying the total completion time of the project.
- Q10: Define Total Float.Ans: It is the difference between the LFT & EFT or the LST & EST. Mathematically:
Total Float = L.F.T – E.F.T or Total Float = L.S.T – E.S.T - Q11: Define Event.Ans: An event shows the completion of activity. It is indicated in the network by a number enclosed in a circle, square or triangle.
- Q12: Define Activity.Ans: The performance of a task or operation is known as activity, for example placing of steel bars etc.
- Q13: Define Critical Activity.Ans: Critical Activity is a task or activity in a project that lies on the critical path, meaning it must be completed on time to avoid delaying the entire project.
- Q14: Define Dummy Activity.Ans: It is an artificial activity shown by a dotted line in a network. It indicates that an activity following it, cannot be started before the completion of proceeding activity.
- Q15: Define Duration.Ans: The estimated time for the performance of an activity is known as duration. It is represented in days, weeks etc. It is denoted by D.
- Q16: Define Arrow and Circle in Critical Path Method.Ans: An arrow represents the sequence of activity on completion of which the whole project can be completed. A circle represents an Event.
- Q17: Define Network Diagram.Ans: It is the time by which activities can be delayed without delaying the total completion time of the project.
- Q18: Define E.S.T.Ans: The earliest start at which an activity can be started is called Earliest Start Time (E.S.T).
- Q19: Define E.F.T.Ans: The earliest time at which an activity can be finished is called Earliest Finish Time (E.F.T).
- Q20: Define L.S.Ans: L.S stands for Latest Start. It is the latest time at which an activity may be started without delaying the completion of the project.
L.S = L.F – D - Q21: Define L.F.T.Ans: L.F.T stands for Latest Finish Time. It is the latest time at which an activity can be finished without delaying the completion of the project.
L.F.T = L.S + D